Calamities
Last-minute request, swift solution

Sometimes we really need to sprint
Some projects are planned months in advance. Others start with a single call at the end of the afternoon.
Last week, we received an urgent request from our partner Flexpumps: three pumps needed to be operational on-site by the next morning.
Our team immediately took action. Equipment was prepared, transport was arranged, and the full logistics were aligned to allow everything to depart that same evening. Thanks to the flexibility and dedication of both teams, the pumps were operational on-site the next morning.
A great example of what is possible when partners trust each other, respond quickly, and collaborate under time pressure.
The timeline of this urgent request
- 16:00 Urgent request received from Flexpumps
- 16:30 Internal coordination and equipment deployment
- 18:30 Pumps prepared and tested
- 20:00 Transport and logistics completed
- 22:00 Equipment loaded for departure
- 23:00 First transport on the way to the site
- 07:00 Arrival on site
- 09:30 Start of first installation and commissioning
- 12:00 All three pumps fully operational
Thanks to all colleagues of Van Heck and Flexpumps for the quick collaboration and commitment.